A disagreement over who should finance electricity infrastructure in newly developed residential estates has exposed a growing challenge in Nigeria’s power distribution system, as the Abuja Electricity Distribution Company (AEDC) seeks stronger investment partnerships with property developers while the Nigerian Electricity Regulatory Commission (NERC) insists that distribution companies must fulfil their infrastructure responsibilities.
The positions emerged at a real estate developers’ stakeholders’ forum in Abuja, where electricity distribution officials, regulators and property industry representatives discussed the difficulties associated with connecting new residential communities to the electricity network.
At the centre of the disagreement is the financial responsibility for transformers, electricity poles, distribution lines and network extensions required to provide power to newly constructed estates.
The issue has significant implications for property developers, who face additional construction expenses when electricity infrastructure is unavailable, and residents, who may be asked to contribute towards facilities that regulations assign to electricity distribution companies.
NERC Says DisCos Must Provide Essential Infrastructure
NERC’s Deputy Manager in the Consumer Protection Department, Mercy Ohamuche, maintained that electricity distribution companies are responsible for providing transformers, poles and extending their networks to serve customers.
She cautioned developers and property owners against assuming that purchasing essential distribution infrastructure is automatically their responsibility.
However, she explained that where a distribution company cannot provide the necessary infrastructure within the required period, customers or third-party investors may finance the project through a formal agreement.
Under such arrangements, the investment can be reimbursed through electricity credits over an agreed period.
This distinction is important because voluntary infrastructure financing under an agreed arrangement is different from compelling consumers to purchase equipment that distribution companies are expected to provide.
For property developers, the terms of such agreements could determine whether infrastructure investment becomes a manageable project expense or an additional financial burden without a clear recovery mechanism.
AEDC Wants Developers Involved Earlier in Power Planning
While NERC emphasised the regulatory responsibilities of distribution companies, AEDC called for stronger collaboration with developers to improve electricity infrastructure planning and service delivery.
The company’s Managing Director and Chief Executive Officer, Chijioke Okwuokenye, identified inadequate funding and poor infrastructure planning as major challenges affecting electricity distribution.
He said closer engagement with property developers would help the company anticipate demand, coordinate investment and prepare its network for expanding residential communities.
Okwuokenye also indicated that AEDC would institutionalise annual engagements involving developers, the Federal Capital Development Authority, the Federal Capital Territory Administration and relevant regulatory agencies.
The company’s Chief Operating Officer, Blessing Ogbe, urged developers to engage AEDC before completing construction rather than waiting until residents were ready to occupy their properties.
She encouraged developers to provide information about projects planned over the next 12 months, alongside their five-year development plans, to help the distributor forecast electricity demand and plan network expansion.
AEDC is also considering a dedicated partnership desk to guide developers on technical requirements, infrastructure planning and investment responsibilities.
Electricity Infrastructure Is Becoming a Property Development Cost
The disagreement highlights a practical problem in Nigeria’s property market: residential developments can be completed without adequate electricity infrastructure to support the needs of their occupants.
When electricity requirements are not considered during the planning stage, developers may encounter delays in connecting buildings to the distribution network.
In some cases, residents move into completed properties only to discover that the available transformer capacity is inadequate or that additional distribution facilities are required.
Such situations can increase construction expenses, delay occupancy and create disagreements between developers, electricity providers and residents.
For homeowners and tenants, the consequences often extend beyond the inconvenience of unreliable electricity.
Households may have to depend on petrol and diesel generators, increasing their monthly energy expenditure. Businesses operating from residential properties may also face higher operating costs, while inadequate power supply can affect the attractiveness of an estate to prospective buyers and tenants.
This makes electricity infrastructure an important consideration in property development rather than a facility that can be addressed after construction.
Metering Becomes Another Major Concern
Beyond infrastructure financing, metering was another important issue discussed at the forum.
NERC maintained that electricity customers must be appropriately metered before connection, warning against unauthorised connections and temporary arrangements that allow residents to consume electricity without proper billing.
Ohamuche also cautioned against shared metering arrangements that create disagreements among occupants over electricity consumption and payment responsibilities.
Individual metering is particularly important in residential estates because it allows households to account for their actual electricity consumption rather than relying on arrangements that distribute bills among several occupants.
The NERC official further warned against transferring outstanding electricity debts from former tenants to new occupants or from previous property owners to new buyers.
She maintained that consumers are entitled to transparent billing, functional meters and appropriate electricity services.
These protections are important in a housing market where tenants and property buyers may have little control over electricity arrangements established by previous occupants or developers.
Developers Seek Better Coordination With AEDC
The Chairman of the Abuja Chapter of the Real Estate Developers Association of Nigeria (REDAN), Tony Okoruwa, identified inadequate coordination between property development and electricity distribution planning as a major source of avoidable delays and additional expenses.
He highlighted insufficient transformer capacity, delayed connections and poorly planned distribution networks among the challenges confronting developers.
Okoruwa called for joint infrastructure assessments and closer coordination between AEDC engineers and developers’ technical teams.
His position reflects the need for electricity planning to begin alongside the design and construction of residential estates.
Early coordination could help developers understand available network capacity, identify additional infrastructure requirements and avoid expensive adjustments after buildings have been completed.
AEDC’s Expanding Network Adds to the Challenge
AEDC distributes electricity across the Federal Capital Territory, Nasarawa, Niger and Kogi states, serving more than 1.3 million customers.
The company disclosed that over 1.13 million customers had been metered, compared with approximately 650,000 in 2023.
It also reported audited revenue of ₦699.48 billion in the 2025 financial year, while energy traded during the period reached 4,749 gigawatt-hours.
These figures illustrate the scale of the company’s operations and the growing importance of network planning as residential and commercial developments expand across its franchise areas.
However, increasing customer numbers and revenue do not automatically translate into adequate electricity infrastructure in every community. Sustained investment, effective planning and regulatory compliance remain necessary to improve service delivery.
Clear Financing Rules Will Determine the Outcome
The discussions between AEDC, NERC and property developers point to a wider question about how Nigeria’s electricity distribution infrastructure should be financed as cities and residential communities continue to expand.
Developers need clear information about the infrastructure they are expected to provide within their estates, while distribution companies must fulfil their regulatory obligations and communicate transparently when additional investment is required.
Equally important is ensuring that residents are not subjected to arbitrary infrastructure charges, unclear reimbursement arrangements or electricity connections that violate consumer protection requirements.
The proposed closer engagement between AEDC and developers could help reduce connection delays and improve electricity planning, but its success will depend on transparent agreements and a clear separation of responsibilities.
For Nigerians buying or renting homes in new estates, the real measure of progress will not be the number of partnership meetings held, but whether completed properties have adequate electricity infrastructure, individual meters and dependable power supply without transferring unjustified costs to residents.